Joule House, Manchester

Project Title
Joule House, Manchester

Sector
Data Centres and Contact Centres

Value
£30m

Client
Telecity

Key Elements

  • New 3.5MW data centre facility, constructed in two phases.
  • Two independent utility power supplies and N+1 generator redundancy
  • High sensitivity smoke detection and high pressure watermist fire suppression
  • Additional capacity introduced in 2nd phase, with no interruption of service in a live data centre
  • Maximum use of ‘free cooling’ via cooling towers for majority of year
  • High efficiency, variable speed, water cooled chillers

CWC were appointed to provide detailed designs for this Colocation Data Centre in Manchester. The development was a 46,500 sqft Tier 3 new build development with N+1 resilience.